Project Manager | Dianne Rice-Hansen, BACTS |
Estimated Costs | $27,096.47 |
Funding Source | UPWP 2020-2021 |
Consultant | James W Sewall Company |
Project Description
Conduct transportation study for Odlin Road / Route 2; this includes compiling and reviewing traffic data for existing conditions, evaluating collision diagrams, preparing a forecast for various scenarios for 2030, analyzing conceptual solution models, and conducting a cost/benefit analysis.
Odlin Road / Route 2 Transportation Study Milestone Schedule
May 18th, 2020 | RFP sent to pre-qualified firms |
May 18-June 5, 2020 | Requests for clarification and/or additional information |
June 10, 2020 | Responses to clarification requests no later than close of business |
June 15th, 2020 | Proposals Due |
June 15-24, 2020 | Selection Committee receives proposals, reviews, and ranks proposals |
June 25 or 26th 2020 | Selection Committee meets and chooses consultant to recommend to PC |
July 21, 2020 | Policy Committee votes on recommended Consultant |
July 21-24, 2020 | Contact Consultant and develop contract |
July 24, 2020 | Notice to proceed to Consultant |
December 22, 2020 | BACTS Odlin Road / Route 2 Transportation Study Presentation |
December 23, 2020 - January 21, 2021 | Public Comment Period - Please see a recording of the discussion of the study at Infrastructure Committee Meeting. Please send all comments or questions to Dianne Rice-Hansen, Transportation Project Manager at dianne.rice-hansen@bactsmpo.org. |
January 31, 2021 | Study finished; report received |
February 28, 2021 | Contract ends |