Project Manager | Sara Devlin, BACTS |
Estimated Costs | $63,359 |
Funding Source | UPWP 2020-2021 |
Estimated Project Schedule | December 2023 |
Consultant | Sebago Technics |
Project Description
Phase 1 – The Consultant identified and evaluated the signal equipment in the BACTS region, developed an assessment management database, and developed a maintenance schedule for all signals.
A link to the inventory database can be found here. Please note that this database is not finalized and is subject to change.
Phase 2 – The Consultant will develop a Traffic Signal Central Management Master Plan for the BACTS region.